Series: Historical shrinkage
How Genesys Cloud calculates historical shrinkage
Genesys Cloud calculates total logged hours for actual shrinkage as the sum of activity category durations and time-off durations. The following activity categories are excluded from the calculation unless the activity occurs within a scheduled shift:
- Offline
- Away
- Idle
Shrinkage calculation by activity category
To view details on a particular activity category that are included in shrinkage, click the corresponding section.
Presence Status |
Included in Shrinkage (Default) | Schedule Shrinkage | Actual Shrinkage |
Break |
Yes |
Hours scheduled for the break activity category of all agents associated with the management unit or the team. |
Actual hours recorded by all agents in the management unit or team for the break activity category. |
Presence Status |
Included in Shrinkage (Default) | Schedule Shrinkage | Actual Shrinkage |
Meal |
Yes |
Hours scheduled for the meal activity category of all agents associated with the management unit or the team. |
Actual hours recorded by all agents in the management unit or team for the meal activity category. |
Presence Status |
Included in Shrinkage (Default) | Schedule Shrinkage | Actual Shrinkage |
Meeting |
Yes |
Hours scheduled for the meeting activity category of all agents associated with the management unit or the team. |
Actual hours recorded by all agents in the management unit or team for the meeting activity category. |
Presence Status |
Included in Shrinkage (Default) | Schedule Shrinkage | Actual Shrinkage |
|
Yes |
Hours scheduled for either of the off queue activity categories of all agents associated with the management unit or the team. |
Actual hours recorded by all agents in the management unit or team for either of the activity categories. |
Presence Status |
Included in Shrinkage (Default) | Schedule Shrinkage | Actual Shrinkage |
Time-off |
Yes |
Hours scheduled for the time-off activity category of all agents associated with the management unit or the team. Note: For full day time-off, Genesys Cloud considers the length of the time-off request as shrinkage duration.
|
Actual hours recorded by all agents in the management unit or team for the time-off activity category. Notes:
|
Example:
If the schedule has a start and end time of 9.00 – 17:00 with:
- Partial time-off activity – 6 hours (9:00 – 15:00)
- On queue activity – 2 hours (15:00 – 17:00)
Then, the scheduled shrinkage is as follows:
- Total schedule = 8 hours
- Schedule shrinkage for time-off = 6 hours
- Total schedule shrinkage = 8 hours
For partial time-off requests, offline presence is excluded when the presence is outside the shift hours and within the shift and time-off window.
If the agent presence in the shift is:
- Offline 8.00–16.00
- On queue 16.00–17.00
Then,
- Actual Shrinkage for unavailable = offline within shift (and outside time-off window) = 1 hour.
- Actual Shrinkage for time-off = 6 hours.
- Total logged hours = time-off request time (6 hours) + on queue time (1 hour) + offline (1 hour) = 8 hours.
- Total actual shrinkage (7 hours) = unavailable shrinkage (1 hour) + time-off shrinkage (6 hours).
- All other presences are included in the actual shrinkage calculation.
If the agent presence is available from 8:00 to 16:00 and remains on queue from 16:00 to 17:00 then,
- Total logged hours = Available time + time-off request time + on queue time.
- 15 hours = 8 hours + 6 hours + 1 hour.
- Total actual shrinkage = Available shrinkage + time-off shrinkage.
- 14 hours = 8 hours + 6 hours.
Presence Status |
Included in Shrinkage (Default) | Schedule Shrinkage | Actual Shrinkage |
Training |
Yes |
Hours scheduled for training activity category of all agents associated with the management unit or the team. |
Actual hours recorded by all agents in the management unit or team for the training category. |
Presence Status |
Included in Shrinkage (Default) | Schedule Shrinkage | Actual Shrinkage |
One of the following statuses:
|
Yes |
Hours scheduled for either unavailable activity category of all agents associated with the management unit or the team. |
Actual hours recorded by all agents in the management unit or team for either of the unavailable categories. Notes:
|
- Paid or unpaid hours are determined from the activity code configuration. For more information, see Configure activity codes.