After you specify the name, start date and end date for the work plan rotation, add work plans to it. For more information, see Work plan rotations overview.

Notes:
  • To create a work plan rotation, you must have configured and enabled work plans.
  • If a work plan is not enabled, you cannot add it to a rotation pattern.
  • You cannot disable or delete an enabled work plan while it is part of a rotation unless you remove it from the rotation first.

To add work plans to a rotation, follow these steps:

  1. Create a new work plan rotation, or open an existing one.
  2. Click the Work Plans tab.
  3. Click Edit. The Edit Work Plans dialog box opens.
    Note: Only enabled work plans in the management unit appear in the Available column.
  4. In the Available column, do one of the following:
    • To add specific work plans, search for and select each work plan to include in the rotation.
    • To add all available work plans to the rotation, click Add All.
  5. Click OK.
  6. Next, add agents to the rotation.