Replace shifts with a scheduled activity

You can replace shifts with a scheduled activity from the schedule editor.

  1. Click Admin.
  2. Under Workforce Management, click Schedules.
  3. Click Menu > Workforce Management > Scheduling > Schedules.
  4. In the upper right corner, click the Management Unit list and select the desired management unit.
  5. Search for the schedule that contains the shifts you want to replace with a scheduled activity and select it from the list. The schedule editor opens.
  6. Select the shifts you want to replace with a scheduled activity.
  7. Select the category or activity with which you want to replace the shifts and do one of the following:
    • Click the arrow at the end of the Select Action list and choose Replace Shifts with Activity.
    • Press Shift+R.
  8. Save, publish, or continue editing the schedule.